Ashoka Grandeur, Bhandup West

by Dhanraj Developers · Bhandup West, Mumbai 400078 · Map

Launched
Jan 20213 yrs 11 mths originally promised
Possession (MahaRERA)
Oct 2028Extended by 3 yrs 10 mths
Concrete structure
30%Mid-construction
Booked (free sale)
36 of 11432% · 91 rehab units
Buildings
10.4 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale36 booked out of 114 units

Rehab91 units for existing members

Total 205 units. Rehab units are not for sale.

Project facts

1 BHK
188
Other units
17
Total units
205
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
1
Free-sale units
114
Rehab units
91

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)30%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 30%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 30%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%30%0%36
100%0%0%35
100%0%0%–
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400078

Projects with 90–400 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400078
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 11 mths5 yrs
Possession date extendedBy 3 yrs 10 mths3 of 3
Possession date (MahaRERA)Oct 2028Apr 2027
Concrete structure (RCC)30%100%
Units booked (free sale)32%97%
MahaRERA complaints (filed by or against the builder)10

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Ashoka Grandeur by Dhanraj Developers is a 205-unit SRA-sanctioned project in Bhandup West, Mumbai 400078, launched in January 2021 with possession due in October 2028. 36 units booked out of 114 units for sale. The concrete structure (RCC) is 30% complete.

Read full summary

Ashoka Grandeur is an SRA-sanctioned project by Dhanraj Developers in Bhandup West, Mumbai 400078, registered with MahaRERA as P51800027876. It was launched in January 2021. It has 205 units in 1 building: 188 homes (1 BHK) and 17 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 205 units, 114 are for sale and 91 are rehab units for existing members.

Its registered possession date is October 2028, extended by 3 years 10 months from the original December 2024. Construction: excavation complete, structure (RCC) 30% complete, final finishes not started.

36 units booked out of 114 units for sale (32%). Since the July 2026 update, 1 more unit has been booked, the reported concrete structure (RCC) has gone from 0% to 30% and the possession date has moved from December 2025 to October 2028.