Vishnu Bhavan Bldg no 4 A wing Valencia CHS and B wing Shree Dutt Guru CHS, Bhandup West

Ready to move

by Shree S S Developers Private Limited · Bhandup West, Mumbai 400078 · Map

Launched
Apr 20215 yrs originally promised
Possession (MahaRERA)
Apr 2027Extended by 1 yr
Concrete structure
100%Ready to move
Booked (free sale)
144 of 144100% · 74 rehab units
Buildings
21.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale144 booked out of 144 units

Rehab74 units for existing members

Total 218 units. Rehab units are not for sale.

Project facts

1 RK
22
1 BHK
189
Other units
7
Total units
218
Buildings
2
Land
1.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
144
Rehab units
74

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 3%Dec 2025: Concrete structure (RCC) 3%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 90%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%144
100%100%90%144
100%3%0%144
100%3%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400078

Projects with 100–450 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400078
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs4 yrs 9 mths
Possession date extendedBy 1 yr2 of 4
Possession date (MahaRERA)Apr 2027Nov 2027
Concrete structure (RCC)100%72%
Units booked (free sale)100%72%
MahaRERA complaints (filed by or against the builder)01

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Vishnu Bhavan Bldg no 4 A wing Valencia CHS and B wing Shree Dutt Guru CHS by Shree S S Developers Private Limited is a 218-unit SRA-sanctioned project in Bhandup West, Mumbai 400078, launched in April 2021 with possession due in April 2027. 144 units booked out of 144 units for sale. The concrete structure (RCC) is complete.

Read full summary

Vishnu Bhavan Bldg no 4 A wing Valencia CHS and B wing Shree Dutt Guru CHS is an SRA-sanctioned project by Shree S S Developers Private Limited in Bhandup West, Mumbai 400078, registered with MahaRERA as P51800029116. It was launched in April 2021. It has 218 units in 2 buildings: 211 homes (1 RK and 1 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 218 units, 144 are for sale and 74 are rehab units for existing members.

Its registered possession date is April 2027, extended by 1 year from the original April 2026. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

144 units booked out of 144 units for sale (100%).