Ajmera Greenfinity, Wadala East

Ready to move

by Ajmera Realty And Infra India Ltd · Wadala East, Mumbai 400037 · Map

Launched
Jan 2021First of 2 phases
Possession (MahaRERA)
Jun 2025 – May 2027Not extended
Concrete structure
100%Weighted across 2 phases
Booked
–
Buildings
327.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
88
2 BHK
256
Total units
344
Buildings
3
Land
27.6 acres
Phases
2
MahaRERA complaints
0

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Ajmera Greenfinity
Ready to move Lapsed
P51800027999172100%–
Building No 6 Ajmera Greenfinity A Wing B Wing
Ready to move
P51800052226172100%94%
Show updates by phase

Ajmera Greenfinity (P51800027999)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%–
100%100%95%–
100%100%95%146

"–" means MahaRERA shows no figure for that update.

Building No 6 Ajmera Greenfinity A Wing B Wing (P51800052226)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%162
100%100%50%160
100%94%20%132
80%0%0%30

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 90%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 50%Dec 2025: Concrete structure (RCC) 97%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 48%Dec 2025: Final finishes 58%Jul 2026: Final finishes 73%Oct 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

How to read construction stages

About this project

Ajmera Greenfinity by Ajmera Realty And Infra India Ltd is a 344-unit BMC-sanctioned project in Wadala East, Mumbai 400037, registered with MahaRERA in 2 phases, with possession dates from June 2025 to May 2027. The concrete structure (RCC) is complete.

Read full summary

Ajmera Greenfinity is a BMC-sanctioned project by Ajmera Realty And Infra India Ltd in Wadala East, Mumbai 400037, registered with MahaRERA as 2 phases (P51800027999, P51800052226). The first phase was launched in January 2021. Together the phases have 344 units in 3 buildings, with 1 and 2 BHK homes as registered with MahaRERA. On MahaRERA, 1 is lapsed and 1 is active.

The phases' registered possession dates run from June 2025 to May 2027; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 95% complete. Both phases have their structure complete.

Ajmera's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA23
Total units across these projects4,563
Completed without extending the possession date10
Completed after an extension0
Lapsed3
Under construction10
Possession date extended on the builder's application2
Typical time from launch to 100% structure4 years 11 months
MahaRERA complaints (filed by or against the builder), all Ajmera projects15 (9 of 23 projects)

See all Ajmera projects →