Ajmera Greenfinity, Wadala East
Ready to move
by Ajmera Realty And Infra India Ltd · Wadala East, Mumbai 400037 · Map
- Launched
- Jan 2021First of 2 phases
- Possession (MahaRERA)
- Jun 2025 – May 2027Not extended
- Concrete structure
- 100%Weighted across 2 phases
- Booked
- –
- Buildings
- 327.6 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 88
- 2 BHK
- 256
- Total units
- 344
- Buildings
- 3
- Land
- 27.6 acres
- Phases
- 2
- MahaRERA complaints
- 0
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Ajmera Greenfinity Ready to move Lapsed | P51800027999 | 172 | 100% | – | |
| Building No 6 Ajmera Greenfinity A Wing B Wing Ready to move | P51800052226 | 172 | 100% | 94% |
Show updates by phase
Ajmera Greenfinity (P51800027999)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | – | |
| 100% | 100% | 95% | – | |
| 100% | 100% | 95% | 146 |
"–" means MahaRERA shows no figure for that update.
Building No 6 Ajmera Greenfinity A Wing B Wing (P51800052226)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 162 | |
| 100% | 100% | 50% | 160 | |
| 100% | 94% | 20% | 132 | |
| 80% | 0% | 0% | 30 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Ajmera Greenfinity by Ajmera Realty And Infra India Ltd is a 344-unit BMC-sanctioned project in Wadala East, Mumbai 400037, registered with MahaRERA in 2 phases, with possession dates from June 2025 to May 2027. The concrete structure (RCC) is complete.
Read full summary
Ajmera Greenfinity is a BMC-sanctioned project by Ajmera Realty And Infra India Ltd in Wadala East, Mumbai 400037, registered with MahaRERA as 2 phases (P51800027999, P51800052226). The first phase was launched in January 2021. Together the phases have 344 units in 3 buildings, with 1 and 2 BHK homes as registered with MahaRERA. On MahaRERA, 1 is lapsed and 1 is active.
The phases' registered possession dates run from June 2025 to May 2027; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 95% complete. Both phases have their structure complete.
Ajmera's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 23 |
|---|---|
| Total units across these projects | 4,563 |
| Completed without extending the possession date | 10 |
| Completed after an extension | 0 |
| Lapsed | 3 |
| Under construction | 10 |
| Possession date extended on the builder's application | 2 |
| Typical time from launch to 100% structure | 4 years 11 months |
| MahaRERA complaints (filed by or against the builder), all Ajmera projects | 15 (9 of 23 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.