Amann Highland Park, Malad East
Lapsed
by Ms Relliance Construction Co · Malad East, Mumbai 400097 · Map
- Launched
- Jan 20214 yrs 5 mths originally promised
- Possession (MahaRERA)
- Oct 2026Extended by 1 yr 4 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 226 of 23198% · 225 in Jul 2026
- Buildings
- 30.8 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 213
- 2 BHK
- 18
- Total units
- 231
- Buildings
- 3
- Land
- 0.8 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 40% | 226 | |
| 100% | 76% | 6% | 225 | |
| 100% | 71% | 6% | 231 | |
| 100% | 39% | 0% | 75 |
"–" means MahaRERA shows no figure for that update.
About this project
Amann Highland Park by Ms Relliance Construction Co is a 231-unit SRA-sanctioned project in Malad East, Mumbai 400097, launched in January 2021; its MahaRERA registration has lapsed. 226 units booked out of total 231 units. The concrete structure (RCC) is complete.
Read full summary
Amann Highland Park is an SRA-sanctioned project by Ms Relliance Construction Co in Malad East, Mumbai 400097, registered with MahaRERA as P51800028085. It was launched in January 2021. It has 231 units in 3 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Its registered possession date is October 2026, extended by 1 year 4 months from the original June 2025. Construction: excavation complete, structure (RCC) complete, final finishes 40% complete.
226 units booked out of total 231 units (98%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 76% to 100%.