Shivshakti Nagar CHS C and D Wing, Kandivali West
Lapsed
by Bombay Slum Redevelopment Corporation Pvt Ltd · Kandivali West, Mumbai 400067 · Map
- Launched
- Feb 20213 yrs 5 mths promised
- Possession (MahaRERA)
- Jul 2024Not extendedWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- –
- Buildings
- 2
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 29
- Other units
- 1
- Total units
- 30
- Buildings
- 2
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 10% | – | |
| 100% | 100% | 10% | – | |
| 100% | 100% | 10% | – | |
| 100% | 100% | 10% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Shivshakti Nagar CHS C and D Wing by Bombay Slum Redevelopment Corporation Pvt Ltd is a 30-unit project in Kandivali West, Mumbai 400067, launched in February 2021; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.
Read full summary
Shivshakti Nagar CHS C and D Wing is a project by Bombay Slum Redevelopment Corporation Pvt Ltd in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800028325. It was launched in February 2021. It has 30 units in 2 buildings: 29 homes (1 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in July 2024. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 10% complete.