Unicorn, Andheri West

Ready to moveLapsed

by Saroj Landmark Realty LLP · Andheri West, Mumbai 400053 · Map

Launched
Feb 20215 yrs 4 mths promised
Possession (MahaRERA)
Jun 2026Not extendedWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
190 of 19498%
Buildings
10.8 acres
MahaRERA complaints
4Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
194
Total units
194
Buildings
1
Land
0.8 acres
Phases
1
MahaRERA complaints
4

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services99%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 99%Dec 2025: Final finishes 99%Jul 2026: Final finishes 99%Oct 2026: Final finishes 99%Excavation 100%Concrete structure (RCC) 100%Final finishes 99%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%99%190
100%100%99%–
100%100%99%–
100%100%99%190

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Unicorn by Saroj Landmark Realty LLP is a 194-unit SRA-sanctioned project in Andheri West, Mumbai 400053, launched in February 2021; its MahaRERA registration has lapsed. 190 units booked out of total 194 units. The concrete structure (RCC) is complete.

Read full summary

Unicorn is an SRA-sanctioned project by Saroj Landmark Realty LLP in Andheri West, Mumbai 400053, registered with MahaRERA as P51800028365. It was launched in February 2021. It has 194 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 99% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

190 units booked out of total 194 units (98%).