by Hf Realty · Vile Parle East, Mumbai 400057 · Map

Launched
Mar 20213 yrs 3 mths originally promised
Possession (MahaRERA)
Jun 2026Extended by 2 yrsWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
18 of 4540%
Buildings
20.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
33
2 BHK
12
Total units
45
Buildings
2
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services99%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 100%Dec 2025: Final finishes 100%Jul 2026: Final finishes 99%Excavation 100%Concrete structure (RCC) 100%Final finishes 99%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%99%18
100%100%100%17
100%100%100%12

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Blossom Residency by Hf Realty is a 45-unit SRA-sanctioned project in Vile Parle East, Mumbai 400057, launched in March 2021; its MahaRERA registration has lapsed. 18 units booked out of total 45 units. The concrete structure (RCC) is complete.

Read full summary

Blossom Residency is an SRA-sanctioned project by Hf Realty in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800028538. It was launched in March 2021. It has 45 units in 2 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2026, after an extension of 2 years from the original June 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 99% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

18 units booked out of total 45 units (40%).