Siddharth Nagar Samata, Goregaon West
Ready to move
by White Water Developers · Goregaon West, Mumbai 400104 · Map
- Launched
- Mar 20212 yrs 1 mth originally promised
- Possession (MahaRERA)
- Apr 2024Extended by 1 yr
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 34 of 4183% · 16 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 3Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale34 booked out of 41 units
Rehab16 units for existing members
Total 57 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 57
- Total units
- 57
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 3
- Free-sale units
- 41
- Rehab units
- 16
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 34 | |
| 100% | 60% | 20% | – | |
| 100% | 60% | 20% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400104
Projects with 20–150 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 1 mth | 4 yrs |
| Possession date extended | By 1 yr | 2 of 3 |
| Possession date (MahaRERA) | Apr 2024 | Jun 2026 |
| Concrete structure (RCC) | 100% | 100% |
| MahaRERA complaints (filed by or against the builder) | 3 | 0 |
The 3 projects
- Shastri Nagar West View CHS Ltd, Goregaon West
- Ghodawat Skystar LLP, Goregaon West
- Goregaon Vihar Darshan Chs Ltd, Goregaon West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shastri Nagar West View CHS Ltd | March 2021 | June 2026 | 95% | – |
| Ghodawat Skystar LLP | December 2021 | June 2026 | 100% | 39 units booked out of total 84 units |
| Goregaon Vihar Darshan Chs Ltd | January 2022 | August 2026 | 100% | 70 units booked out of total 85 units |
About this project
Siddharth Nagar Samata by White Water Developers is a 57-unit MHADA-sanctioned project in Goregaon West, Mumbai 400104, launched in March 2021 with possession due in April 2024. 34 units booked out of 41 units for sale. The concrete structure (RCC) is complete.
Read full summary
Siddharth Nagar Samata is a MHADA-sanctioned project by White Water Developers in Goregaon West, Mumbai 400104, registered with MahaRERA as P51800028598. It was launched in March 2021. It has 57 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 57 units, 41 are for sale and 16 are rehab units for existing members.
Possession was due in April 2024, after an extension of 1 year from the original April 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
34 units booked out of 41 units for sale (83%).