Goregaon Vihar Darshan Chs Ltd, Goregaon West
Ready to moveLapsed
by Silver Lifespaces Private Limited · Goregaon West, Mumbai 400104 · Map
- Launched
- Jan 20221 yr 6 mths originally promised
- Possession (MahaRERA)
- Aug 2026Extended by 3 yrs 1 mthWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- 70 of 8582%
- Buildings
- 20.4 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 85
- Total units
- 85
- Buildings
- 2
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 70 | |
| 100% | 100% | 100% | 70 | |
| 100% | 100% | 50% | 62 | |
| 100% | 59% | 0% | 49 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400104
Projects with 40–200 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 6 mths | 3 yrs 3 mths |
| Possession date extended | By 3 yrs 1 mth | 3 of 4 |
| Possession date (MahaRERA) | Aug 2026 | Dec 2025 |
| Concrete structure (RCC) | 100% | 98% |
| Units booked | 82% | 66% |
| MahaRERA complaints (filed by or against the builder) | 1 | 2 |
The 4 projects
- Ghodawat Skystar LLP, Goregaon West
- 36 Allure, Goregaon West
- Asmi Legend, Goregaon West
- Siddharth Nagar Samata, Goregaon West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ghodawat Skystar LLP | December 2021 | June 2026 | 100% | 39 units booked out of total 84 units |
| 36 Allure | December 2021 | June 2025 | 67% | 86 units booked out of total 124 units |
| Asmi Legend | December 2021 | December 2027 | 97% | 106 units booked out of total 168 units |
| Siddharth Nagar Samata | March 2021 | April 2024 | 100% | 34 units booked out of 41 units for sale |
About this project
Goregaon Vihar Darshan Chs Ltd by Silver Lifespaces Private Limited is an 85-unit MHADA-sanctioned project in Goregaon West, Mumbai 400104, launched in January 2022; its MahaRERA registration has lapsed. 70 units booked out of total 85 units. The concrete structure (RCC) is complete.
Read full summary
Goregaon Vihar Darshan Chs Ltd is a MHADA-sanctioned project by Silver Lifespaces Private Limited in Goregaon West, Mumbai 400104, registered with MahaRERA as P51800032448. It was launched in January 2022. It has 85 units in 2 buildings, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in August 2026, after an extension of 3 years 1 month from the original July 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
70 units booked out of total 85 units (82%).