Yamuna Maharani Heights, Kandivali West

Lapsed

by K B Associates · Kandivali West, Mumbai 400067 · Map

Launched
Mar 20213 yrs 6 mths originally promised
Possession (MahaRERA)
Sep 2026Extended by 2 yrsWhat does Lapsed mean?
Concrete structure
78%Mid-construction
Booked (free sale)
33 of 3985% · 27 rehab units
Buildings
20.4 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale33 booked out of 39 units

Rehab27 units for existing members

Total 66 units. Rehab units are not for sale.

Project facts

1 BHK
32
2 BHK
15
3 BHK
14
4 BHK
1
Other units
4
Total units
66
Buildings
2
Land
0.4 acres
Phases
1
MahaRERA complaints
2
Free-sale units
39
Rehab units
27

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)78%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 78%Dec 2025: Concrete structure (RCC) 78%Jul 2026: Concrete structure (RCC) 78%Oct 2026: Concrete structure (RCC) 78%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 78%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%78%0%33
100%78%0%33
100%78%0%33
100%78%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Yamuna Maharani Heights by K B Associates is a 66-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in March 2021; its MahaRERA registration has lapsed. 33 units booked out of 39 units for sale. The concrete structure (RCC) is 78% complete.

Read full summary

Yamuna Maharani Heights is a BMC-sanctioned project by K B Associates in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800028829. It was launched in March 2021. It has 66 units in 2 buildings: 62 homes (1, 2, 3 and 4 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 66 units, 39 are for sale and 27 are rehab units for existing members.

Possession was due in September 2026, after an extension of 2 years from the original September 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 78% complete, final finishes not started.

33 units booked out of 39 units for sale (85%).