V Residence, Kalbadevi

Lapsed

by Pankaj Shyam Chawla · Kalbadevi, Mumbai 400002 · Map

Launched
Apr 20213 yrs 9 mths originally promised
Possession (MahaRERA)
Mar 2026Extended by 1 yr 2 mthsWhat does Lapsed mean?
Concrete structure
91%Mid-construction
Booked
53 of 53100%
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
27
2 BHK
17
3 BHK
6
Other units
3
Total units
53
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)91%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 0%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 91%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 91%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%91%90%53
0%0%0%–
0%0%0%–
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

V Residence by Pankaj Shyam Chawla is a 53-unit BMC-sanctioned project in Kalbadevi, Mumbai 400002, launched in April 2021; its MahaRERA registration has lapsed. 53 units booked out of total 53 units. The concrete structure (RCC) is 91% complete.

Read full summary

V Residence is a BMC-sanctioned project by Pankaj Shyam Chawla in Kalbadevi, Mumbai 400002, registered with MahaRERA as P51800028929. It was launched in April 2021. It has 53 units in 1 building: 50 homes (1, 2 and 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in March 2026, after an extension of 1 year 2 months from the original January 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 91% complete, final finishes 90% complete.

53 units booked out of total 53 units (100%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 91%.