by Spenta Enclave Private Limited · Chembur, Mumbai 400071 · Map

Launched
Apr 20213 yrs 8 mths originally promised
Possession (MahaRERA)
Dec 2029Extended by 5 yrs
Concrete structure
0%Early stage
Booked
20 of 20210% · 22 in Jul 2026
Buildings
10.1 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
51
2 BHK
151
Total units
202
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation90%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 50%Dec 2025: Excavation 50%Jul 2026: Excavation 60%Oct 2026: Excavation 90%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 90%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
90%0%0%20
60%0%0%22
50%0%0%22
50%0%0%10

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Ornata - Amber by Spenta Enclave Private Limited is a 202-unit SRA-sanctioned project in Chembur, Mumbai 400071, launched in April 2021 with possession due in December 2029. 20 units booked out of total 202 units. Work on the concrete structure (RCC) has not started.

Read full summary

Ornata - Amber is an SRA-sanctioned project by Spenta Enclave Private Limited in Chembur, Mumbai 400071, registered with MahaRERA as P51800028964. It was launched in April 2021. It has 202 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, extended by 5 years from the original December 2024. Construction: excavation 90% complete, structure (RCC) not started, final finishes not started.

20 units booked out of total 202 units (10%).

Spenta's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA10
Total units across these projects1,369
Completed without extending the possession date1
Completed after an extension2
Lapsed0
Under construction7
Possession date extended on the builder's application7
Typical time from launch to 100% structure7 years 5 months
MahaRERA complaints (filed by or against the builder), all Spenta projects43 (6 of 10 projects)