KCD Jogesh Eva, Jogeshwari East
Lapsed
by KCD Heritage Private Limited · Jogeshwari East, Mumbai 400060 · Map
- Launched
- Jun 20212 yrs 6 mths originally promised
- Possession (MahaRERA)
- Dec 2025Extended by 2 yrsWhat does Lapsed mean?
- Concrete structure
- 67%Mid-construction
- Booked (free sale)
- 20 of 2195% · 20 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 5Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale20 booked out of 21 units
Rehab20 units for existing members
Total 41 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 14
- 2 BHK
- 14
- 3 BHK
- 13
- Total units
- 41
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 5
- Free-sale units
- 21
- Rehab units
- 20
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 67% | 0% | 20 | |
| 100% | 67% | 0% | 20 | |
| 100% | 67% | 0% | – | |
| 100% | 67% | 0% | 20 |
"–" means MahaRERA shows no figure for that update.
About this project
KCD Jogesh Eva by KCD Heritage Private Limited is a 41-unit BMC-sanctioned project in Jogeshwari East, Mumbai 400060, launched in June 2021; its MahaRERA registration has lapsed. 20 units booked out of 21 units for sale. The concrete structure (RCC) is 67% complete.
Read full summary
KCD Jogesh Eva is a BMC-sanctioned project by KCD Heritage Private Limited in Jogeshwari East, Mumbai 400060, registered with MahaRERA as P51800029753. It was launched in June 2021. It has 41 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 41 units, 21 are for sale and 20 are rehab units for existing members.
Possession was due in December 2025, after an extension of 2 years from the original December 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 67% complete, final finishes not started.
20 units booked out of 21 units for sale (95%).