Veridian at Emerald Isle, Chandivali

Ready to move

by Larsen & Toubro Ltd. (Realty Division) · Chandivali, Mumbai 400072 · Map

Launched
Jul 2021First of 5 phases
Possession (MahaRERA)
Apr 2025 – Sep 2027Extended in 3 of 5 phases
Concrete structure
100%Weighted across 5 phases
Booked
650 of 68495% · 662 in Jul 2026
Buildings
90.2 acres
MahaRERA complaints
12Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
293
2 BHK
283
3 BHK
108
Total units
684
Buildings
9
Land
0.2 acres
Phases
5
MahaRERA complaints
12

The 5 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Veridian at Emerald Isle 12C
Ready to move
P5180002988878100%88%
Veridian at Emerald Isle 14A and 14B
Ready to move
P51800029892154100%92%
Veridian at Emerald Isle 13A and 13B
Ready to move
P51800029893154100%94%
Veridian at Emerald Isle 12A and 12B
Ready to move Lapsed
P51800031441152100%98%
Veridian at Emerald Isle 11A and 11B
Ready to move Lapsed
P51800031775146100%99%
Show updates by phase

Veridian at Emerald Isle 12C (P51800029888)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%69
100%100%100%71
100%100%100%76
100%20%0%76

"–" means MahaRERA shows no figure for that update.

Veridian at Emerald Isle 14A and 14B (P51800029892)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%142
100%78%0%144
100%78%0%–
100%78%0%152

"–" means MahaRERA shows no figure for that update.

Veridian at Emerald Isle 13A and 13B (P51800029893)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%145
100%100%100%153
100%100%100%153
100%38%0%153

"–" means MahaRERA shows no figure for that update.

Veridian at Emerald Isle 12A and 12B (P51800031441)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%98%149
100%100%98%149
100%100%98%149
100%32%0%149

"–" means MahaRERA shows no figure for that update.

Veridian at Emerald Isle 11A and 11B (P51800031775)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%145
100%100%100%145
100%100%100%145
100%25%0%145

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 41%Dec 2025: Concrete structure (RCC) 95%Jul 2026: Concrete structure (RCC) 95%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 77%Jul 2026: Final finishes 77%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

How to read construction stages

About this project

Veridian at Emerald Isle by Larsen & Toubro Ltd. (Realty Division) (L&T Realty) is a 684-unit BMC-sanctioned project in Chandivali, Mumbai 400072, registered with MahaRERA in 5 phases, with possession dates from April 2025 to September 2027. 650 units booked out of total 684 units. The concrete structure (RCC) is complete.

Read full summary

Veridian at Emerald Isle is a BMC-sanctioned project by Larsen & Toubro Ltd. (Realty Division) in Chandivali, Mumbai 400072, registered with MahaRERA as 5 phases (P51800029888, P51800029892, P51800029893, P51800031441, P51800031775). The first phase was launched in July 2021. Together the phases have 684 units in 9 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. On MahaRERA, 3 are active and 2 are lapsed.

The phases' registered possession dates run from April 2025 to September 2027; 3 of 5 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 100% complete. All 5 phases have their structure complete.

650 units booked out of total 684 units (95%).

L&T Realty's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA29
Total units across these projects4,949
Completed without extending the possession date11
Completed after an extension3
Lapsed3
Under construction12
Possession date extended on the builder's application8
Typical time from launch to 100% structure4 years 5 months
MahaRERA complaints (filed by or against the builder), all L&T Realty projects114 (16 of 29 projects)

See all L&T Realty projects →