Shubh Parshwa, Mulund West
by S. Siddharth Construction Co. (Panchshil) · Mulund West, Mumbai 400080 · Map
- Launched
- Jul 20212 yrs 5 mths originally promised
- Possession (MahaRERA)
- Jun 2027Extended by 3 yrs 6 mths
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 82 of 8794% · 24 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale82 booked out of 87 units
Rehab24 units for existing members
Total 111 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 59
- 2 BHK
- 35
- Other units
- 17
- Total units
- 111
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 87
- Rehab units
- 24
- Reserved units
- 43
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 20% | 82 | |
| 100% | 100% | 20% | 82 | |
| 100% | 95% | 20% | 80 | |
| 100% | 95% | 20% | 12 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400080
Projects with 40–200 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 5 mths | 2 yrs 11 mths |
| Possession date extended | By 3 yrs 6 mths | 3 of 3 |
| Possession date (MahaRERA) | Jun 2027 | Mar 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 94% | 53% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Nami CHS Ltd, Mulund West
- Marigold Aangan, Mulund West
- Devhans Mahesh Krupa, Mulund West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Nami CHS Ltd | April 2021 | March 2026 | 14% | 32 units booked out of 41 units for sale |
| Marigold Aangan | April 2021 | October 2026 | 100% | 40 units booked out of total 76 units |
| Devhans Mahesh Krupa | February 2022 | June 2025 | 100% | 23 units booked out of total 65 units |
About this project
Shubh Parshwa by S. Siddharth Construction Co. (Panchshil) is a 111-unit SRA-sanctioned project in Mulund West, Mumbai 400080, launched in July 2021 with possession due in June 2027. 82 units booked out of 87 units for sale. The concrete structure (RCC) is complete.
Read full summary
Shubh Parshwa is an SRA-sanctioned project by S. Siddharth Construction Co. (Panchshil) in Mulund West, Mumbai 400080, registered with MahaRERA as P51800029898. It was launched in July 2021. It has 111 units in 1 building: 94 homes (1 and 2 BHK) and 17 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 111 units, 87 are for sale and 24 are rehab units for existing members.
Its registered possession date is June 2027, extended by 3 years 6 months from the original December 2023. Construction: excavation complete, structure (RCC) complete, final finishes 20% complete.
82 units booked out of 87 units for sale (94%).