Marigold Aangan, Mulund West

Lapsed

by Marigold Constructions · Mulund West, Mumbai 400080 · Map

Launched
Apr 20212 yrs 11 mths originally promised
Possession (MahaRERA)
Oct 2026Extended by 2 yrs 7 mthsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
40 of 7653%
Buildings
10.4 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
19
1 BHK
48
Other units
9
Total units
76
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 10%Dec 2025: Final finishes 50%Jul 2026: Final finishes 50%Oct 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 100%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%50%40
100%100%50%40
100%100%50%40
100%100%10%29

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400080

Projects with 30–150 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 11 mths2 yrs 10 mths
Possession date extendedBy 2 yrs 7 mths3 of 3
Possession date (MahaRERA)Oct 2026Mar 2026
Concrete structure (RCC)100%100%
Units booked53%78%
MahaRERA complaints (filed by or against the builder)10

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Marigold Aangan by Marigold Constructions is a 76-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in April 2021; its MahaRERA registration has lapsed. 40 units booked out of total 76 units. The concrete structure (RCC) is complete.

Read full summary

Marigold Aangan is a BMC-sanctioned project by Marigold Constructions in Mulund West, Mumbai 400080, registered with MahaRERA as P51800029006. It was launched in April 2021. It has 76 units in 1 building: 67 homes (1 RK and 1 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Its registered possession date is October 2026, extended by 2 years 7 months from the original March 2024. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.

40 units booked out of total 76 units (53%).