HS Pearl, Mulund East

Ready to moveLapsed

by HS Property Developers · Mulund East, Mumbai 400081 · Map

Launched
Jul 20213 yrs 5 mths promised
Possession (MahaRERA)
Dec 2024Not extendedWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
–
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
13
2 BHK
23
3 BHK
1
5+ BHK
1
Other units
17
Total units
55
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 95%Dec 2025: Final finishes 95%Jul 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%–
100%100%95%–
100%100%95%49

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

HS Pearl by HS Property Developers is a 55-unit project in Mulund East, Mumbai 400081, launched in July 2021; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

HS Pearl is a project by HS Property Developers in Mulund East, Mumbai 400081, registered with MahaRERA as P51800029946. It was launched in July 2021. It has 55 units in 1 building: 38 homes (1, 2, 3 and 5+ BHK) and 17 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2024. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.