Skip to main content

Simra Residency, Kurla West

Lapsed

by Vinayaka Realtors And Developers · Kurla West, Mumbai 400070 · Map

Launched
Jul 20213 yrs 5 mths promised
Possession (MahaRERA)
Dec 2024Not extendedWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked
–
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
2
1 BHK
38
Total units
40
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%–
100%0%0%–
100%0%0%–
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Simra Residency by Vinayaka Realtors And Developers is a 40-unit project in Kurla West, Mumbai 400070, launched in July 2021; its MahaRERA registration has lapsed. Work on the concrete structure (RCC) has not started.

Read full summary

Simra Residency is a project by Vinayaka Realtors And Developers in Kurla West, Mumbai 400070, registered with MahaRERA as P51800029958. It was launched in July 2021. It has 40 units in 1 building, with 1 RK and 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2024. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) not started, final finishes not started.