Soham Majesty, Borivali West

Lapsed

by Laxmikant Ramchandra Sawant · Borivali West, Mumbai 400092 · Map

Launched
Aug 20212 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2024Extended by 1 yrWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
6 of 1638%
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
4
1 BHK
1
2 BHK
11
Total units
16
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services80%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 80%Dec 2025: Final finishes 80%Jul 2026: Final finishes 80%Oct 2026: Final finishes 80%Excavation 100%Concrete structure (RCC) 100%Final finishes 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%80%6
100%100%80%–
100%100%80%–
100%100%80%6

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Soham Majesty by Laxmikant Ramchandra Sawant is a 16-unit project in Borivali West, Mumbai 400092, launched in August 2021; its MahaRERA registration has lapsed. 6 units booked out of total 16 units. The concrete structure (RCC) is complete.

Read full summary

Soham Majesty is a project by Laxmikant Ramchandra Sawant in Borivali West, Mumbai 400092, registered with MahaRERA as P51800030226. It was launched in August 2021. It has 16 units in 1 building, with 1 RK, 1 BHK and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2024, after an extension of 1 year from the original December 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.

6 units booked out of total 16 units (38%).