Soham Majesty, Borivali West
Lapsed
by Laxmikant Ramchandra Sawant · Borivali West, Mumbai 400092 · Map
- Launched
- Aug 20212 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2024Extended by 1 yrWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 6 of 1638%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 4
- 1 BHK
- 1
- 2 BHK
- 11
- Total units
- 16
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 80% | 6 | |
| 100% | 100% | 80% | – | |
| 100% | 100% | 80% | – | |
| 100% | 100% | 80% | 6 |
"–" means MahaRERA shows no figure for that update.
About this project
Soham Majesty by Laxmikant Ramchandra Sawant is a 16-unit project in Borivali West, Mumbai 400092, launched in August 2021; its MahaRERA registration has lapsed. 6 units booked out of total 16 units. The concrete structure (RCC) is complete.
Read full summary
Soham Majesty is a project by Laxmikant Ramchandra Sawant in Borivali West, Mumbai 400092, registered with MahaRERA as P51800030226. It was launched in August 2021. It has 16 units in 1 building, with 1 RK, 1 BHK and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2024, after an extension of 1 year from the original December 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.
6 units booked out of total 16 units (38%).