Marathon Neopark Ashoka, Bhandup West
by Marathon Nextgen Realty Ltd · Bhandup West, Mumbai 400078 · Map
- Launched
- Sep 2021First of 3 phases
- Possession (MahaRERA)
- Dec 2025 – Jun 2028Extended in 1 of 3 phases
- Concrete structure
- 96%Weighted across 3 phases
- Booked
- 410 of 47287% · 302 in Jul 2026
- Buildings
- 30.8 acres
- MahaRERA complaints
- 3Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 131
- 1 BHK
- 341
- Total units
- 472
- Buildings
- 3
- Land
- 0.8 acres
- Phases
- 3
- MahaRERA complaints
- 3
The 3 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Marathon Neopark Ashoka Wing B Nearing possession Lapsed | P51800030751 | 128 | 100% | 94% | |
| Marathon Neopark Ashoka Wing C Mid-construction | P51800030752 | 151 | 86% | 72% | |
| Marathon Neopark Ashoka Wing A Nearing possession Lapsed | P51800031073 | 193 | 100% | 94% |
Show updates by phase
Marathon Neopark Ashoka Wing B (P51800030751)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 68% | 120 | |
| 100% | 100% | 68% | 120 | |
| 100% | 100% | 68% | 120 | |
| 100% | 57% | 0% | 120 |
"–" means MahaRERA shows no figure for that update.
Marathon Neopark Ashoka Wing C (P51800030752)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 86% | 0% | 108 | |
| 100% | 39% | 0% | 0 | |
| 100% | 39% | 0% | 0 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Marathon Neopark Ashoka Wing A (P51800031073)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 43% | 182 | |
| 100% | 100% | 43% | 182 | |
| 100% | 100% | 37% | 182 | |
| 100% | 96% | 0% | 181 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Compared with 5 similar projects in PIN 400078
Projects with 200–1,000 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 3 mths | 6 yrs |
| Possession date extended | Yes | 2 of 5 |
| Possession date (MahaRERA) | Dec 2025 – Jun 2028 | Dec 2027 |
| Concrete structure (RCC) | 96% | 100% |
| Units booked | 87% | 94% |
| MahaRERA complaints (filed by or against the builder) | 3 | 0 |
The 5 projects
- Bella, Bhandup West
- Ganesh Bhuvan CHS Ltd, Bhandup West
- Shraddha Vardaan, Bhandup West
- Shree Vrindavan SRA CHS Ltd, Bhandup West
- Shraddha Classic, Bhandup West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Bella | June 2021 | Jul 2025 | 100% | 430 units booked out of total 445 units |
| Ganesh Bhuvan CHS Ltd | December 2021 | December 2027 | 88% | 192 units booked out of 192 units for sale |
| Shraddha Vardaan | April 2021 | December 2027 | 100% | 681 units booked out of total 723 units |
| Shree Vrindavan SRA CHS Ltd | March 2021 | December 2028 | 95% | 283 units booked out of 332 units for sale |
| Shraddha Classic | March 2021 | June 2027 | 100% | 469 units booked out of 500 units for sale |
About this project
Marathon Neopark Ashoka by Marathon Nextgen Realty Ltd is a 472-unit project in Bhandup West, Mumbai 400078, registered with MahaRERA in 3 phases, with possession dates from December 2025 to June 2028. 410 units booked out of total 472 units. The concrete structure (RCC) is 96% complete.
Read full summary
Marathon Neopark Ashoka is a project by Marathon Nextgen Realty Ltd in Bhandup West, Mumbai 400078, registered with MahaRERA as 3 phases (P51800030751, P51800030752, P51800031073). The first phase was launched in September 2021. Together the phases have 472 units in 3 buildings, with 1 RK and 1 BHK homes as registered with MahaRERA. On MahaRERA, 2 are lapsed and 1 is active.
The phases' registered possession dates run from December 2025 to June 2028; 1 of 3 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 96% complete and final finishes 36% complete. 2 of the 3 phases have their structure complete.
410 units booked out of total 472 units (87%). Since the July 2026 update, 108 more units have been booked.
Marathon's track record in Mumbai
MahaRERA projects registered 2017–2024 in Mumbai
| Projects registered with MahaRERA | 11 |
|---|---|
| Total units across these projects | 818 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 2 |
| Lapsed | 6 |
| Under construction | 3 |
| Possession date extended on the builder's application | 5 |
| Typical time from launch to 100% structure | 4 years 6 months |
| MahaRERA complaints (filed by or against the builder), all Marathon projects | 11 (5 of 11 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.