Marathon Neopark Ashoka, Bhandup West

by Marathon Nextgen Realty Ltd · Bhandup West, Mumbai 400078 · Map

Launched
Sep 2021First of 3 phases
Possession (MahaRERA)
Dec 2025 – Jun 2028Extended in 1 of 3 phases
Concrete structure
96%Weighted across 3 phases
Booked
410 of 47287% · 302 in Jul 2026
Buildings
30.8 acres
MahaRERA complaints
3Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
131
1 BHK
341
Total units
472
Buildings
3
Land
0.8 acres
Phases
3
MahaRERA complaints
3

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Marathon Neopark Ashoka Wing B
Nearing possession Lapsed
P51800030751128100%94%
Marathon Neopark Ashoka Wing C
Mid-construction
P5180003075215186%72%
Marathon Neopark Ashoka Wing A
Nearing possession Lapsed
P51800031073193100%94%
Show updates by phase

Marathon Neopark Ashoka Wing B (P51800030751)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%68%120
100%100%68%120
100%100%68%120
100%57%0%120

"–" means MahaRERA shows no figure for that update.

Marathon Neopark Ashoka Wing C (P51800030752)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%86%0%108
100%39%0%0
100%39%0%0
100%0%0%0

"–" means MahaRERA shows no figure for that update.

Marathon Neopark Ashoka Wing A (P51800031073)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%43%182
100%100%43%182
100%100%37%182
100%96%0%181

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)96%
Finishes, lifts and services36%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 55%Dec 2025: Concrete structure (RCC) 80%Jul 2026: Concrete structure (RCC) 80%Oct 2026: Concrete structure (RCC) 96%Dec 2024: Final finishes 0%Dec 2025: Final finishes 34%Jul 2026: Final finishes 36%Oct 2026: Final finishes 36%Excavation 100%Concrete structure (RCC) 96%Final finishes 36%

How to read construction stages

Compared with 5 similar projects in PIN 400078

Projects with 200–1,000 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400078
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 3 mths6 yrs
Possession date extendedYes2 of 5
Possession date (MahaRERA)Dec 2025 – Jun 2028Dec 2027
Concrete structure (RCC)96%100%
Units booked87%94%
MahaRERA complaints (filed by or against the builder)30

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Marathon Neopark Ashoka by Marathon Nextgen Realty Ltd is a 472-unit project in Bhandup West, Mumbai 400078, registered with MahaRERA in 3 phases, with possession dates from December 2025 to June 2028. 410 units booked out of total 472 units. The concrete structure (RCC) is 96% complete.

Read full summary

Marathon Neopark Ashoka is a project by Marathon Nextgen Realty Ltd in Bhandup West, Mumbai 400078, registered with MahaRERA as 3 phases (P51800030751, P51800030752, P51800031073). The first phase was launched in September 2021. Together the phases have 472 units in 3 buildings, with 1 RK and 1 BHK homes as registered with MahaRERA. On MahaRERA, 2 are lapsed and 1 is active.

The phases' registered possession dates run from December 2025 to June 2028; 1 of 3 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 96% complete and final finishes 36% complete. 2 of the 3 phases have their structure complete.

410 units booked out of total 472 units (87%). Since the July 2026 update, 108 more units have been booked.

Marathon's track record in Mumbai

MahaRERA projects registered 2017–2024 in Mumbai

Projects registered with MahaRERA11
Total units across these projects818
Completed without extending the possession date0
Completed after an extension2
Lapsed6
Under construction3
Possession date extended on the builder's application5
Typical time from launch to 100% structure4 years 6 months
MahaRERA complaints (filed by or against the builder), all Marathon projects11 (5 of 11 projects)