Marathon projects in Mumbai
MahaRERA projects by Marathon registered 2017–2024 in Mumbai.
| Projects registered with MahaRERA | 11 |
|---|---|
| Total units across these projects | 818 |
Full record
MahaRERA projects registered 2017–2024 in Mumbai
| Completed without extending the possession date | 0 |
|---|---|
| Completed after an extension | 2 |
| Lapsed | 6 |
| Under construction | 3 |
| Possession date extended on the builder's application | 5 |
| Typical time from launch to 100% structure | 4 years 6 months |
| MahaRERA complaints (filed by or against the builder), all Marathon projects | 11 (5 of 11 projects) |
What these mean
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Where they build: Bhandup West (3) · Mulund West (2) · Lower Parel (2)
Under construction
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Marathon Monte Carlo · 2 phases | Mulund West | Ready to move | Dec 2023 – Dec 2026 | – |
| Marathon Neopark Ashoka · 3 phases | Bhandup West | Mid-construction | Dec 2025 – Jun 2028 | 410 units booked out of total 472 units |
| Marathon Neosquare A | Bhandup West | Ready to move | April 2027 | 136 units booked out of total 150 units |
Completed
| Project | Village | Status |
|---|---|---|
| Mahakaleshwar | Bhandup West | Completed |
| Marathon Futurex 1 | Lower Parel | Completed |
Lapsed
| Project | Village | Status |
|---|---|---|
| Marathon Futurex | Lower Parel | Lapsed |
| Marathon Monteplaza | Mulund West | Lapsed |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.
Is a project grouped wrongly or a figure out of date? Tell us