Charkop Arihant Prabhu Cooperative Housing Society Limited, Kandivali West

Lapsed

by Sandhya Kshitij Builders Private Limited · Kandivali West, Mumbai 400067 · Map

Launched
Sep 20213 yrs 5 mths originally promised
Possession (MahaRERA)
Sep 2025Extended by 7 mthsWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked
–
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
42
3 BHK
3
Other units
7
Total units
52
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Work not started as of Oct 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%–
0%0%0%–
0%0%0%–
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Charkop Arihant Prabhu Cooperative Housing Society Limited by Sandhya Kshitij Builders Private Limited is a 52-unit MHADA-sanctioned project in Kandivali West, Mumbai 400067, launched in September 2021; its MahaRERA registration has lapsed. Work on the concrete structure (RCC) has not started.

Read full summary

Charkop Arihant Prabhu Cooperative Housing Society Limited is a MHADA-sanctioned project by Sandhya Kshitij Builders Private Limited in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800030873. It was launched in September 2021. It has 52 units in 1 building: 45 homes (2 and 3 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in September 2025, after an extension of 7 months from the original February 2025. That date has passed and no further extension has been recorded. Construction: excavation not started, structure (RCC) not started, final finishes not started.