Charkop Arihant Prabhu Cooperative Housing Society Limited, Kandivali West
Lapsed
by Sandhya Kshitij Builders Private Limited · Kandivali West, Mumbai 400067 · Map
- Launched
- Sep 20213 yrs 5 mths originally promised
- Possession (MahaRERA)
- Sep 2025Extended by 7 mthsWhat does Lapsed mean?
- Concrete structure
- 0%Early stage
- Booked
- –
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 42
- 3 BHK
- 3
- Other units
- 7
- Total units
- 52
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Work not started as of Oct 2026
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Charkop Arihant Prabhu Cooperative Housing Society Limited by Sandhya Kshitij Builders Private Limited is a 52-unit MHADA-sanctioned project in Kandivali West, Mumbai 400067, launched in September 2021; its MahaRERA registration has lapsed. Work on the concrete structure (RCC) has not started.
Read full summary
Charkop Arihant Prabhu Cooperative Housing Society Limited is a MHADA-sanctioned project by Sandhya Kshitij Builders Private Limited in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800030873. It was launched in September 2021. It has 52 units in 1 building: 45 homes (2 and 3 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in September 2025, after an extension of 7 months from the original February 2025. That date has passed and no further extension has been recorded. Construction: excavation not started, structure (RCC) not started, final finishes not started.