Skip to main content

Jeandveekedarnath, Dahisar

by Je And Vee Infrastructure · Dahisar, Mumbai 400068 · Map

Launched
Sep 20213 yrs 7 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 1 yr 8 mths
Concrete structure
0%Early stage
Booked
104 of 22047%
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
128
2 BHK
92
Total units
220
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%104
100%0%0%–
100%0%0%–
100%0%0%104

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400068

Projects with 100–450 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400068
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 7 mths4 yrs
Possession date extendedBy 1 yr 8 mths2 of 3
Possession date (MahaRERA)Dec 2026Apr 2026
Concrete structure (RCC)0%75%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Jeandveekedarnath by Je And Vee Infrastructure is a 220-unit MHADA-sanctioned project in Dahisar, Mumbai 400068, launched in September 2021 with possession due in December 2026. 104 units booked out of total 220 units. Work on the concrete structure (RCC) has not started.

Read full summary

Jeandveekedarnath is a MHADA-sanctioned project by Je And Vee Infrastructure in Dahisar, Mumbai 400068, registered with MahaRERA as P51800030984. It was launched in September 2021. It has 220 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 1 year 8 months from the original April 2025. Construction: excavation complete, structure (RCC) not started, final finishes not started.

104 units booked out of total 220 units (47%).