Corporate Annexe, Goregaon East

Lapsed

by Vardhman Sonal Venture · Goregaon East, Mumbai 400063 · Map

Launched
Sep 20212 yrs 3 mths originally promised
Possession (MahaRERA)
Dec 2024Extended by 1 yrWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
33 of 9335%
Buildings
10.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
93
Total units
93
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services80%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 60%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 80%Jul 2026: Final finishes 80%Oct 2026: Final finishes 80%Excavation 100%Concrete structure (RCC) 100%Final finishes 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%80%33
100%100%80%–
100%100%80%–
100%60%0%33

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Corporate Annexe by Vardhman Sonal Venture is a 93-unit project in Goregaon East, Mumbai 400063, launched in September 2021; its MahaRERA registration has lapsed. 33 units booked out of total 93 units. The concrete structure (RCC) is complete.

Read full summary

Corporate Annexe is a project by Vardhman Sonal Venture in Goregaon East, Mumbai 400063, registered with MahaRERA as P51800030989. It was launched in September 2021. It has 93 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2024, after an extension of 1 year from the original December 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.

33 units booked out of total 93 units (35%).