One Crystal, Ghatkopar East

Lapsed

by Goldnest Spaces LLP · Ghatkopar East, Mumbai 400077 · Map

Launched
Oct 20214 yrs 2 mths promised
Possession (MahaRERA)
Dec 2025Not extendedWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
92 of 13270%
Buildings
10.1 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
132
Total units
132
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 0%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%92
0%0%0%–
0%0%0%–
0%0%0%125

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

One Crystal by Goldnest Spaces LLP is a 132-unit SRA-sanctioned project in Ghatkopar East, Mumbai 400077, launched in October 2021; its MahaRERA registration has lapsed. 92 units booked out of total 132 units. The concrete structure (RCC) is complete.

Read full summary

One Crystal is an SRA-sanctioned project by Goldnest Spaces LLP in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800031074. It was launched in October 2021. It has 132 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes not started.

92 units booked out of total 132 units (70%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 100%.