Crystal Palladian 207, Ghatkopar West

Lapsed

by Sri Sai Nidhi Realtors Private Limited · Ghatkopar West, Mumbai 400086 · Map

Launched
Oct 20214 yrs 2 mths originally promised
Possession (MahaRERA)
Jun 2026Extended by 6 mthsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
139 of 18874%
Buildings
10.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
188
Total units
188
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%139
100%100%0%139
100%90%0%136
0%0%0%105

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Crystal Palladian 207 by Sri Sai Nidhi Realtors Private Limited is a 188-unit SRA-sanctioned project in Ghatkopar West, Mumbai 400086, launched in October 2021; its MahaRERA registration has lapsed. 139 units booked out of total 188 units. The concrete structure (RCC) is complete.

Read full summary

Crystal Palladian 207 is an SRA-sanctioned project by Sri Sai Nidhi Realtors Private Limited in Ghatkopar West, Mumbai 400086, registered with MahaRERA as P51800031122. It was launched in October 2021. It has 188 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2026, after an extension of 6 months from the original December 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes not started.

139 units booked out of total 188 units (74%).