Dotom Isle-Shakti, Malad West

Ready to moveLapsed

by M/S. Dotom Real Estate · Malad West, Mumbai 400095 · Map

Launched
Nov 20213 yrs 1 mth originally promised
Possession (MahaRERA)
Jun 2025Extended by 6 mthsWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked (free sale)
88 of 9395%
Buildings
15.7 acres
MahaRERA complaints
4Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale88 booked out of 93 units

Land-owner share32 units, not for sale

Total 125 units. Land-owner units are not for sale.

Project facts

1 BHK
35
2 BHK
55
3 BHK
19
Other units
16
Total units
125
Buildings
1
Land
5.7 acres
Phases
1
MahaRERA complaints
4
Free-sale units
93
Land-owner share (not for sale)
32

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 80%Dec 2025: Final finishes 90%Jul 2026: Final finishes 90%Oct 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%88
100%100%90%–
100%100%90%–
100%100%80%44

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Dotom Isle-Shakti by M/S. Dotom Real Estate is a 125-unit SRA-sanctioned project in Malad West, Mumbai 400095, launched in November 2021; its MahaRERA registration has lapsed. 88 units booked out of 93 units for sale. The concrete structure (RCC) is complete.

Read full summary

Dotom Isle-Shakti is an SRA-sanctioned project by M/S. Dotom Real Estate in Malad West, Mumbai 400095, registered with MahaRERA as P51800031765. It was launched in November 2021. It has 125 units in 1 building: 109 homes (1, 2 and 3 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 125 units, 93 are for sale and 32 are the land-owner's share, not for sale.

Possession was due in June 2025, after an extension of 6 months from the original December 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

88 units booked out of 93 units for sale (95%).