Dotom Isle-Shakti, Malad West
Ready to moveLapsed
by M/S. Dotom Real Estate · Malad West, Mumbai 400095 · Map
- Launched
- Nov 20213 yrs 1 mth originally promised
- Possession (MahaRERA)
- Jun 2025Extended by 6 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 88 of 9395%
- Buildings
- 15.7 acres
- MahaRERA complaints
- 4Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale88 booked out of 93 units
Land-owner share32 units, not for sale
Total 125 units. Land-owner units are not for sale.
Project facts
- 1 BHK
- 35
- 2 BHK
- 55
- 3 BHK
- 19
- Other units
- 16
- Total units
- 125
- Buildings
- 1
- Land
- 5.7 acres
- Phases
- 1
- MahaRERA complaints
- 4
- Free-sale units
- 93
- Land-owner share (not for sale)
- 32
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 88 | |
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | – | |
| 100% | 100% | 80% | 44 |
"–" means MahaRERA shows no figure for that update.
About this project
Dotom Isle-Shakti by M/S. Dotom Real Estate is a 125-unit SRA-sanctioned project in Malad West, Mumbai 400095, launched in November 2021; its MahaRERA registration has lapsed. 88 units booked out of 93 units for sale. The concrete structure (RCC) is complete.
Read full summary
Dotom Isle-Shakti is an SRA-sanctioned project by M/S. Dotom Real Estate in Malad West, Mumbai 400095, registered with MahaRERA as P51800031765. It was launched in November 2021. It has 125 units in 1 building: 109 homes (1, 2 and 3 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 125 units, 93 are for sale and 32 are the land-owner's share, not for sale.
Possession was due in June 2025, after an extension of 6 months from the original December 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
88 units booked out of 93 units for sale (95%).