D Solitaire, Santacruz East
Lapsed
by Krishnan And Kamal Associates · Santacruz East, Mumbai 400029 · Map
- Launched
- Nov 20211 yr 4 mths originally promised
- Possession (MahaRERA)
- Jun 2026Extended by 3 yrs 3 mthsWhat does Lapsed mean?
- Concrete structure
- 87%Mid-construction
- Booked
- 107 of 13579%
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 6
- 1 BHK
- 114
- 2 BHK
- 15
- Total units
- 135
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Reserved units
- 81
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 87% | 0% | 107 | |
| 100% | 87% | 0% | 107 | |
| 100% | 87% | 0% | 107 | |
| 100% | 87% | 0% | 21 |
"–" means MahaRERA shows no figure for that update.
About this project
D Solitaire by Krishnan And Kamal Associates is a 135-unit SRA-sanctioned project in Santacruz East, Mumbai 400029, launched in November 2021; its MahaRERA registration has lapsed. 107 units booked out of total 135 units. The concrete structure (RCC) is 87% complete.
Read full summary
D Solitaire is an SRA-sanctioned project by Krishnan And Kamal Associates in Santacruz East, Mumbai 400029, registered with MahaRERA as P51800031850. It was launched in November 2021. It has 135 units in 1 building, with 1 RK, 1 BHK and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2026, after an extension of 3 years 3 months from the original March 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 87% complete, final finishes not started.
107 units booked out of total 135 units (79%).