Casaroyale, Andheri West
Lapsed
by Fairmont Constructions Private Limited · Andheri West, Mumbai 400058 · Map
- Launched
- Dec 20212 yrs originally promised
- Possession (MahaRERA)
- Dec 2024Extended by 1 yrWhat does Lapsed mean?
- Concrete structure
- 0%Early stage
- Booked
- –
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 1
- 3 BHK
- 11
- Total units
- 12
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Casaroyale by Fairmont Constructions Private Limited is a 12-unit project in Andheri West, Mumbai 400058, launched in December 2021; its MahaRERA registration has lapsed. Work on the concrete structure (RCC) has not started.
Read full summary
Casaroyale is a project by Fairmont Constructions Private Limited in Andheri West, Mumbai 400058, registered with MahaRERA as P51800031988. It was launched in December 2021. It has 12 units in 1 building, with 1 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2024, after an extension of 1 year from the original December 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) not started, final finishes not started.