Building no.1 Wing H Olive, Kandivali East

Lapsed

by S D Corporation Pvt Ltd · Kandivali East, Mumbai 400101 · Map

Launched
Dec 20213 yrs originally promised
Possession (MahaRERA)
Dec 2025Extended by 1 yrWhat does Lapsed mean?
Concrete structure
35%Mid-construction
Booked
15 of 4038%
Buildings
10.5 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
40
Total units
40
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)35%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 35%Dec 2025: Concrete structure (RCC) 35%Jul 2026: Concrete structure (RCC) 35%Oct 2026: Concrete structure (RCC) 35%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 35%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%35%0%15
100%35%0%–
100%35%0%–
100%35%0%15

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Building no.1 Wing H Olive by S D Corporation Pvt Ltd is a 40-unit MHADA-sanctioned project in Kandivali East, Mumbai 400101, launched in December 2021; its MahaRERA registration has lapsed. 15 units booked out of total 40 units. The concrete structure (RCC) is 35% complete.

Read full summary

Building no.1 Wing H Olive is a MHADA-sanctioned project by S D Corporation Pvt Ltd in Kandivali East, Mumbai 400101, registered with MahaRERA as P51800031998. It was launched in December 2021. It has 40 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025, after an extension of 1 year from the original December 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 35% complete, final finishes not started.

15 units booked out of total 40 units (38%).