Skip to main content

Geetanjali Paradise, Malad West

Ready to move

by Vasundhara Develocus LLP · Malad West, Mumbai 400064 · Map

Launched
Dec 20215 yrs promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
100%Ready to move
Booked (free sale)
37 of 6062% · 55 rehab units
Buildings
20.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale37 booked out of 60 units

Rehab55 units for existing members

Total 115 units. Rehab units are not for sale.

Project facts

1 RK
1
1 BHK
42
2 BHK
53
3 BHK
16
Other units
3
Total units
115
Buildings
2
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
60
Rehab units
55

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 75%Dec 2025: Final finishes 75%Jul 2026: Final finishes 100%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%37
100%100%100%37
100%100%75%37
100%100%75%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400064

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400064
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs3 yrs 10 mths
Possession date extendedNo4 of 6
Possession date (MahaRERA)Dec 2026Dec 2026
Concrete structure (RCC)100%100%
Units booked (free sale)62%97%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Geetanjali Paradise by Vasundhara Develocus LLP is a 115-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in December 2021 with possession due in December 2026. 37 units booked out of 60 units for sale. The concrete structure (RCC) is complete.

Read full summary

Geetanjali Paradise is a BMC-sanctioned project by Vasundhara Develocus LLP in Malad West, Mumbai 400064, registered with MahaRERA as P51800032045. It was launched in December 2021. It has 115 units in 2 buildings: 112 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 115 units, 60 are for sale and 55 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

37 units booked out of 60 units for sale (62%).