Siddha Shila, Malad West

Lapsed

by RKE Builders & Developers · Malad West, Mumbai 400064 · Map

Launched
Jun 20223 yrs 6 mths promised
Possession (MahaRERA)
Dec 2025Not extendedWhat does Lapsed mean?
Concrete structure
60%Mid-construction
Booked
99 of 99100%
Buildings
10.3 acres
MahaRERA complaints
10Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
64
3 BHK
31
Other units
4
Total units
99
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
10

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)60%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 60%Dec 2025: Concrete structure (RCC) 60%Jul 2026: Concrete structure (RCC) 60%Oct 2026: Concrete structure (RCC) 60%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 60%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%60%0%99
100%60%0%99
100%60%0%99
100%60%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400064

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400064
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 6 mths3 yrs 4 mths
Possession date extendedNo3 of 6
Possession date (MahaRERA)Dec 2025Oct 2026
Concrete structure (RCC)60%100%
Units booked100%97%
MahaRERA complaints (filed by or against the builder)100

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Siddha Shila by RKE Builders & Developers is a 99-unit SRA-sanctioned project in Malad West, Mumbai 400064, launched in June 2022; its MahaRERA registration has lapsed. 99 units booked out of total 99 units. The concrete structure (RCC) is 60% complete.

Read full summary

Siddha Shila is an SRA-sanctioned project by RKE Builders & Developers in Malad West, Mumbai 400064, registered with MahaRERA as P51800046233. It was launched in June 2022. It has 99 units in 1 building: 95 homes (2 and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 60% complete, final finishes not started.

99 units booked out of total 99 units (100%).