Nirvaana Pearl, Grant Road

Lapsed

by Nirvaana Lifespace LLP · Grant Road, Mumbai 400007 · Map

Launched
Dec 20213 yrs 6 mths originally promised
Possession (MahaRERA)
Jun 2026Extended by 1 yrWhat does Lapsed mean?
Concrete structure
88%Mid-construction
Booked (free sale)
40 of 6760% · 40 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale40 booked out of 67 units

Rehab40 units for existing members

Total 107 units. Rehab units are not for sale.

Project facts

1 BHK
28
2 BHK
53
3 BHK
14
Other units
12
Total units
107
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
67
Rehab units
40

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation95%
Concrete structure (slabs)88%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 95%Jul 2026: Excavation 95%Oct 2026: Excavation 95%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 88%Jul 2026: Concrete structure (RCC) 88%Oct 2026: Concrete structure (RCC) 88%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 95%Concrete structure (RCC) 88%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
95%88%0%40
95%88%0%40
95%88%0%40
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400007

Projects with 40–200 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400007
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 6 mths4 yrs 10 mths
Possession date extendedBy 1 yr1 of 3
Possession date (MahaRERA)Jun 2026Jul 2028
Concrete structure (RCC)88%100%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Nirvaana Pearl by Nirvaana Lifespace LLP is a 107-unit MHADA-sanctioned project in Grant Road, Mumbai 400007, launched in December 2021; its MahaRERA registration has lapsed. 40 units booked out of 67 units for sale. The concrete structure (RCC) is 88% complete.

Read full summary

Nirvaana Pearl is a MHADA-sanctioned project by Nirvaana Lifespace LLP in Grant Road, Mumbai 400007, registered with MahaRERA as P51800032083. It was launched in December 2021. It has 107 units in 1 building: 95 homes (1, 2 and 3 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 107 units, 67 are for sale and 40 are rehab units for existing members.

Possession was due in June 2026, after an extension of 1 year from the original June 2025. That date has passed and no further extension has been recorded. Construction: excavation 95% complete, structure (RCC) 88% complete, final finishes not started.

40 units booked out of 67 units for sale (60%).