- Launched
- Dec 20213 yrs 6 mths originally promised
- Possession (MahaRERA)
- Jun 2026Extended by 1 yrWhat does Lapsed mean?
- Concrete structure
- 88%Mid-construction
- Booked (free sale)
- 40 of 6760% · 40 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale40 booked out of 67 units
Rehab40 units for existing members
Total 107 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 28
- 2 BHK
- 53
- 3 BHK
- 14
- Other units
- 12
- Total units
- 107
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 67
- Rehab units
- 40
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 95% | 88% | 0% | 40 | |
| 95% | 88% | 0% | 40 | |
| 95% | 88% | 0% | 40 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400007
Projects with 40–200 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 6 mths | 4 yrs 10 mths |
| Possession date extended | By 1 yr | 1 of 3 |
| Possession date (MahaRERA) | Jun 2026 | Jul 2028 |
| Concrete structure (RCC) | 88% | 100% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Mustafa Palace, Grant Road
- Marq, Grant Road
- Central Park, Grant Road
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Mustafa Palace | February 2022 | December 2026 | 100% | 22 units booked out of 36 units for sale |
| Marq | June 2022 | November 2028 | 40% | 44 units booked out of total 81 units |
| Central Park | September 2022 | Jul 2028 | 100% | – |
About this project
Nirvaana Pearl by Nirvaana Lifespace LLP is a 107-unit MHADA-sanctioned project in Grant Road, Mumbai 400007, launched in December 2021; its MahaRERA registration has lapsed. 40 units booked out of 67 units for sale. The concrete structure (RCC) is 88% complete.
Read full summary
Nirvaana Pearl is a MHADA-sanctioned project by Nirvaana Lifespace LLP in Grant Road, Mumbai 400007, registered with MahaRERA as P51800032083. It was launched in December 2021. It has 107 units in 1 building: 95 homes (1, 2 and 3 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 107 units, 67 are for sale and 40 are rehab units for existing members.
Possession was due in June 2026, after an extension of 1 year from the original June 2025. That date has passed and no further extension has been recorded. Construction: excavation 95% complete, structure (RCC) 88% complete, final finishes not started.
40 units booked out of 67 units for sale (60%).