Mahavir Majesty, Kandivali West
Ready to move
by Mahavir Builders · Kandivali West, Mumbai 400067 · Map
- Launched
- Dec 20214 yrs originally promised
- Possession (MahaRERA)
- Sep 2026Extended by 9 mths
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 36 of 6258% · 59 rehab units
- Buildings
- 20.6 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale36 booked out of 62 units
Rehab59 units for existing members
Total 121 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 15
- 2 BHK
- 55
- 3 BHK
- 15
- Other units
- 36
- Total units
- 121
- Buildings
- 2
- Land
- 0.6 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 62
- Rehab units
- 59
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 36 | |
| 100% | 98% | 63% | – | |
| 100% | 98% | 63% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400067
Projects with 40–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs | 5 yrs |
| Possession date extended | By 9 mths | 1 of 3 |
| Possession date (MahaRERA) | Sep 2026 | Mar 2027 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 58% | 71% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Om Shreenath Krupa Chs Ltd, Kandivali West
- Orion Heights, Kandivali West
- Prathamesh Elite, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Om Shreenath Krupa Chs Ltd | December 2021 | December 2026 | 100% | 21 units booked out of 28 units for sale |
| Orion Heights | April 2022 | March 2027 | 100% | 73 units booked out of 111 units for sale |
| Prathamesh Elite | June 2021 | December 2027 | 75% | 77 units booked out of total 108 units |
About this project
Mahavir Majesty by Mahavir Builders is a 121-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in December 2021 with possession due in September 2026. 36 units booked out of 62 units for sale. The concrete structure (RCC) is complete.
Read full summary
Mahavir Majesty is a BMC-sanctioned project by Mahavir Builders in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800032166. It was launched in December 2021. It has 121 units in 2 buildings: 85 homes (1, 2 and 3 BHK) and 36 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 121 units, 62 are for sale and 59 are rehab units for existing members.
Possession was due in September 2026, after an extension of 9 months from the original December 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
36 units booked out of 62 units for sale (58%).