Prathamesh Elite, Kandivali West
by Shree Sainath Developers · Kandivali West, Mumbai 400067 · Map
- Launched
- Jun 20215 yrs 6 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 1 yr
- Concrete structure
- 75%Mid-construction
- Booked
- 77 of 10871% · 60 in Jul 2026
- Buildings
- 11.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 40
- 2 BHK
- 43
- 3 BHK
- 21
- Other units
- 4
- Total units
- 108
- Buildings
- 1
- Land
- 1.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 75% | 0% | 77 | |
| 100% | 75% | 0% | 60 | |
| 100% | 41% | 0% | 60 | |
| 100% | 30% | 0% | 32 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400067
Projects with 50–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 6 mths | 4 yrs 6 mths |
| Possession date extended | By 1 yr | 2 of 4 |
| Possession date (MahaRERA) | Dec 2027 | Nov 2026 |
| Concrete structure (RCC) | 75% | 100% |
| Units booked | 71% | 81% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Gauri Excellency Nx, Kandivali West
- Mahavir Majesty, Kandivali West
- Om Shreenath Krupa Chs Ltd, Kandivali West
- Shreeji Sky Rise Tower, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Gauri Excellency Nx | July 2021 | June 2026 | 18% | 183 units booked out of total 188 units |
| Mahavir Majesty | December 2021 | September 2026 | 100% | 36 units booked out of 62 units for sale |
| Om Shreenath Krupa Chs Ltd | December 2021 | December 2026 | 100% | 21 units booked out of 28 units for sale |
| Shreeji Sky Rise Tower | December 2021 | December 2026 | 100% | 206 units booked out of total 237 units |
About this project
Prathamesh Elite by Shree Sainath Developers is a 108-unit SRA-sanctioned project in Kandivali West, Mumbai 400067, launched in June 2021 with possession due in December 2027. 77 units booked out of total 108 units. The concrete structure (RCC) is 75% complete.
Read full summary
Prathamesh Elite is an SRA-sanctioned project by Shree Sainath Developers in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800029737. It was launched in June 2021. It has 108 units in 1 building: 104 homes (1, 2 and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, extended by 1 year from the original December 2026. Construction: excavation complete, structure (RCC) 75% complete, final finishes not started.
77 units booked out of total 108 units (71%). Since the July 2026 update, 17 more units have been booked.