M/S Shri Sai Lata Flat Owners Co-Op Hsg Soc Ltd, Chembur
Ready to moveLapsed
by Parth Developers · Chembur, Mumbai 400089 · Map
- Launched
- Jan 20223 yrs 11 mths promised
- Possession (MahaRERA)
- Dec 2025Not extendedWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- –
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 15
- 2 BHK
- 15
- 3 BHK
- 4
- Total units
- 34
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | 18 |
"–" means MahaRERA shows no figure for that update.
About this project
M/S Shri Sai Lata Flat Owners Co-Op Hsg Soc Ltd by Parth Developers is a 34-unit project in Chembur, Mumbai 400089, launched in January 2022; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.
Read full summary
M/S Shri Sai Lata Flat Owners Co-Op Hsg Soc Ltd is a project by Parth Developers in Chembur, Mumbai 400089, registered with MahaRERA as P51800032481. It was launched in January 2022. It has 34 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.