M/S Shri Sai Lata Flat Owners Co-Op Hsg Soc Ltd, Chembur

Ready to moveLapsed

by Parth Developers · Chembur, Mumbai 400089 · Map

Launched
Jan 20223 yrs 11 mths promised
Possession (MahaRERA)
Dec 2025Not extendedWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
–
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
15
2 BHK
15
3 BHK
4
Total units
34
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 90%Dec 2025: Final finishes 90%Jul 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%–
100%100%90%–
100%100%90%18

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

M/S Shri Sai Lata Flat Owners Co-Op Hsg Soc Ltd by Parth Developers is a 34-unit project in Chembur, Mumbai 400089, launched in January 2022; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

M/S Shri Sai Lata Flat Owners Co-Op Hsg Soc Ltd is a project by Parth Developers in Chembur, Mumbai 400089, registered with MahaRERA as P51800032481. It was launched in January 2022. It has 34 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.