Lodha Kandivali Project, Kandivali East
by Lodha Developers Limited · Kandivali East, Mumbai 400101 · Map
- Launched
- Jan 2022First of 2 phases
- Possession (MahaRERA)
- Feb 2028Extended in both phases
- Concrete structure
- 100%Weighted across 2 phases
- Booked
- 233 of 24197%
- Buildings
- 20.4 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 2
- 1 BHK
- 4
- 2 BHK
- 84
- 3 BHK
- 147
- Other units
- 4
- Total units
- 241
- Buildings
- 2
- Land
- 0.4 acres
- Phases
- 2
- MahaRERA complaints
- 1
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Lodha Kandivali Project - Tower 5 Completed | P51800032605 | 88 | 100% | 98% | |
| Lodha Kandivali Project-Tower 1 Nearing possession | P51800045908 | 149 | 100% | 96% |
Show updates by phase
Lodha Kandivali Project - Tower 5 (P51800032605)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 86 | |
| 100% | 100% | 100% | 86 | |
| 100% | 100% | 100% | 86 | |
| 100% | 100% | 0% | 78 |
"–" means MahaRERA shows no figure for that update.
Lodha Kandivali Project-Tower 1 (P51800045908)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 15% | 147 | |
| 100% | 93% | 5% | 147 | |
| 100% | 80% | 5% | 146 | |
| 100% | 22% | 0% | 134 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Lodha Kandivali Project by Lodha Developers Limited is a 241-unit BMC-sanctioned project in Kandivali East, Mumbai 400101, registered with MahaRERA in 2 phases, with possession due in February 2028. 233 units booked out of total 241 units. The concrete structure (RCC) is complete.
Read full summary
Lodha Kandivali Project is a BMC-sanctioned project by Lodha Developers Limited in Kandivali East, Mumbai 400101, registered with MahaRERA as 2 phases (P51800032605, P51800045908). The first phase was launched in January 2022. Together the phases have 241 units in 2 buildings: 237 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. On MahaRERA, 1 is completed and 1 is active.
The registered possession date is February 2028; both phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 47% complete. Both phases have their structure complete.
233 units booked out of total 241 units (97%).
Lodha's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 85 |
|---|---|
| Total units across these projects | 15,101 |
| Completed without extending the possession date | 31 |
| Completed after an extension | 13 |
| Lapsed | 0 |
| Under construction | 41 |
| Possession date extended on the builder's application | 34 |
| Typical time from launch to 100% structure | 5 years 10 months |
| MahaRERA complaints (filed by or against the builder), all Lodha projects | 242 (38 of 85 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.