Lodha Kandivali Project, Kandivali East

by Lodha Developers Limited · Kandivali East, Mumbai 400101 · Map

Launched
Jan 2022First of 2 phases
Possession (MahaRERA)
Feb 2028Extended in both phases
Concrete structure
100%Weighted across 2 phases
Booked
233 of 24197%
Buildings
20.4 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
2
1 BHK
4
2 BHK
84
3 BHK
147
Other units
4
Total units
241
Buildings
2
Land
0.4 acres
Phases
2
MahaRERA complaints
1

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Lodha Kandivali Project - Tower 5
Completed
P5180003260588100%98%
Lodha Kandivali Project-Tower 1
Nearing possession
P51800045908149100%96%
Show updates by phase

Lodha Kandivali Project - Tower 5 (P51800032605)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%86
100%100%100%86
100%100%100%86
100%100%0%78

"–" means MahaRERA shows no figure for that update.

Lodha Kandivali Project-Tower 1 (P51800045908)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%15%147
100%93%5%147
100%80%5%146
100%22%0%134

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services47%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 51%Dec 2025: Concrete structure (RCC) 87%Jul 2026: Concrete structure (RCC) 96%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 40%Jul 2026: Final finishes 40%Oct 2026: Final finishes 47%Excavation 100%Concrete structure (RCC) 100%Final finishes 47%

How to read construction stages

About this project

Lodha Kandivali Project by Lodha Developers Limited is a 241-unit BMC-sanctioned project in Kandivali East, Mumbai 400101, registered with MahaRERA in 2 phases, with possession due in February 2028. 233 units booked out of total 241 units. The concrete structure (RCC) is complete.

Read full summary

Lodha Kandivali Project is a BMC-sanctioned project by Lodha Developers Limited in Kandivali East, Mumbai 400101, registered with MahaRERA as 2 phases (P51800032605, P51800045908). The first phase was launched in January 2022. Together the phases have 241 units in 2 buildings: 237 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. On MahaRERA, 1 is completed and 1 is active.

The registered possession date is February 2028; both phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 47% complete. Both phases have their structure complete.

233 units booked out of total 241 units (97%).

Lodha's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA85
Total units across these projects15,101
Completed without extending the possession date31
Completed after an extension13
Lapsed0
Under construction41
Possession date extended on the builder's application34
Typical time from launch to 100% structure5 years 10 months
MahaRERA complaints (filed by or against the builder), all Lodha projects242 (38 of 85 projects)

See all Lodha projects →