Vkg Park Estate, Andheri East

Lapsed

by Krishna Developers Pvt Ltd · Andheri East, Mumbai 400099 · Map

Launched
Jan 20223 yrs 11 mths promised
Possession (MahaRERA)
Dec 2025Not extendedWhat does Lapsed mean?
Concrete structure
35%Mid-construction
Booked
–
Buildings
41.8 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
135
1 BHK
21
2 BHK
2
3 BHK
2
4 BHK
1
5+ BHK
1
Total units
162
Buildings
4
Land
1.8 acres
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)35%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 35%Dec 2025: Concrete structure (RCC) 35%Jul 2026: Concrete structure (RCC) 35%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 35%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%35%0%–
100%35%0%–
100%35%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Vkg Park Estate by Krishna Developers Pvt Ltd is a 162-unit BMC-sanctioned project in Andheri East, Mumbai 400099, launched in January 2022; its MahaRERA registration has lapsed. The concrete structure (RCC) is 35% complete.

Read full summary

Vkg Park Estate is a BMC-sanctioned project by Krishna Developers Pvt Ltd in Andheri East, Mumbai 400099, registered with MahaRERA as P51800032677. It was launched in January 2022. It has 162 units in 4 buildings, with 1 RK, 1 BHK, 2 BHK, 3 BHK, 4 BHK and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 35% complete, final finishes not started.