Regent Grandeur, Jogeshwari East
Ready to moveLapsed
by Regent Associates · Jogeshwari East, Mumbai 400060 · Map
- Launched
- Jan 20223 yrs 11 mths promised
- Possession (MahaRERA)
- Dec 2025Not extendedWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 64 of 7486% · 11 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale64 booked out of 74 units
Rehab11 units for existing members
Total 85 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 4
- 2 BHK
- 50
- 3 BHK
- 3
- Other units
- 28
- Total units
- 85
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 74
- Rehab units
- 11
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 64 | |
| 100% | 100% | 95% | 64 | |
| 100% | 100% | 95% | 64 | |
| 100% | 100% | 0% | 24 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400060
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 11 mths | 3 yrs 2 mths |
| Possession date extended | No | 3 of 3 |
| Possession date (MahaRERA) | Dec 2025 | Aug 2026 |
| Concrete structure (RCC) | 100% | 100% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Om Shivalaya CHS Ltd, Jogeshwari East
- Sudarshan Landmark, Jogeshwari East
- Satyam, Jogeshwari East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Om Shivalaya CHS Ltd | January 2022 | December 2026 | 100% | 15 units booked out of 21 units for sale |
| Sudarshan Landmark | September 2021 | December 2023 | 100% | – |
| Satyam | June 2022 | August 2026 | 100% | 54 units booked out of total 58 units |
About this project
Regent Grandeur by Regent Associates is an 85-unit BMC-sanctioned project in Jogeshwari East, Mumbai 400060, launched in January 2022; its MahaRERA registration has lapsed. 64 units booked out of 74 units for sale. The concrete structure (RCC) is complete.
Read full summary
Regent Grandeur is a BMC-sanctioned project by Regent Associates in Jogeshwari East, Mumbai 400060, registered with MahaRERA as P51800032790. It was launched in January 2022. It has 85 units in 1 building: 57 homes (1, 2 and 3 BHK) and 28 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 85 units, 74 are for sale and 11 are rehab units for existing members.
Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
64 units booked out of 74 units for sale (86%).