9, Business Bay, Malad West

Ready to moveLapsed

by Leo Realtors · Malad West, Mumbai 400064 · Map

Launched
Feb 20223 yrs 1 mth originally promised
Possession (MahaRERA)
Mar 2026Extended by 1 yrWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked (free sale)
232 of 30476%
Buildings
11 acre
MahaRERA complaints
5Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale232 booked out of 304 units

Land-owner share9 units, not for sale

Total 313 units. Land-owner units are not for sale.

Project facts

Other units
313
Total units
313
Buildings
1
Land
1 acre
Phases
1
MahaRERA complaints
5
Free-sale units
304
Land-owner share (not for sale)
9

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 80%Dec 2025: Final finishes 95%Jul 2026: Final finishes 95%Oct 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%232
100%100%95%232
100%100%95%232
100%100%80%173

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

9, Business Bay by Leo Realtors is a 313-unit project in Malad West, Mumbai 400064, launched in February 2022; its MahaRERA registration has lapsed. 232 units booked out of 304 units for sale. The concrete structure (RCC) is complete.

Read full summary

9, Business Bay is a project by Leo Realtors in Malad West, Mumbai 400064, registered with MahaRERA as P51800032829. It was launched in February 2022. It has 313 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 313 units, 304 are for sale and 9 are the land-owner's share, not for sale.

Possession was due in March 2026, after an extension of 1 year from the original March 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

232 units booked out of 304 units for sale (76%).