Skip to main content

Ajmera Manhattan, Wadala East

by Ajmera Realty And Infra India Ltd · Wadala East, Mumbai 400037 · Map

Launched
Feb 2022First of 2 phases
Possession (MahaRERA)
Jun 2027 – Jul 2030Not extended
Concrete structure
55%Weighted across 2 phases
Booked
798 of 98381% · 806 in Jul 2026
Buildings
327.6 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
476
3 BHK
392
4 BHK
81
Other units
34
Total units
983
Buildings
3
Land
27.6 acres
Phases
2
MahaRERA complaints
2

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Ajmera Manhattan Building 3A And 3B
Nearing possession
P51800032948525100%97%
Ajmera Manhattan Building 4A And 4B
Early stage
PR11800025008224240%62%
Show updates by phase

Ajmera Manhattan Building 3A And 3B (P51800032948)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%10%525
100%100%10%525
100%80%2%524
100%0%0%345

"–" means MahaRERA shows no figure for that update.

Ajmera Manhattan Building 4A And 4B (PR1180002500822)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
10%0%0%273
10%0%0%281
0%0%0%15

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation60%
Concrete structure (slabs)55%
Finishes, lifts and services6%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 55%Jul 2026: Excavation 60%Oct 2026: Excavation 60%Dec 2025: Concrete structure (RCC) 44%Jul 2026: Concrete structure (RCC) 55%Oct 2026: Concrete structure (RCC) 55%Dec 2025: Final finishes 1%Jul 2026: Final finishes 6%Oct 2026: Final finishes 6%Excavation 60%Concrete structure (RCC) 55%Final finishes 6%

How to read construction stages

About this project

Ajmera Manhattan by Ajmera Realty And Infra India Ltd is a 983-unit BMC-sanctioned project in Wadala East, Mumbai 400037, registered with MahaRERA in 2 phases, with possession dates from June 2027 to July 2030. 798 units booked out of total 983 units. The concrete structure (RCC) is 55% complete.

Read full summary

Ajmera Manhattan is a BMC-sanctioned project by Ajmera Realty And Infra India Ltd in Wadala East, Mumbai 400037, registered with MahaRERA as 2 phases (P51800032948, PR1180002500822). The first phase was launched in February 2022. Together the phases have 983 units in 3 buildings: 949 homes (2, 3 and 4 BHK) and 34 other units (shops, offices or not given by type), as registered with MahaRERA. Both phases are active on MahaRERA.

The phases' registered possession dates run from June 2027 to July 2030; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 55% complete and final finishes 6% complete. Neither phase has its structure complete.

798 units booked out of total 983 units (81%).

Ajmera's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA23
Total units across these projects4,563
Completed without extending the possession date10
Completed after an extension0
Lapsed3
Under construction10
Possession date extended on the builder's application2
Typical time from launch to 100% structure4 years 11 months
MahaRERA complaints (filed by or against the builder), all Ajmera projects15 (9 of 23 projects)

See all Ajmera projects →