Sidhivinayak Flora, Chembur
by Sidhivinayak Constructions · Chembur, Mumbai 400071 · Map
- Launched
- Feb 20222 yrs 6 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 2 yrs 8 mths
- Concrete structure
- 95%Mid-construction
- Booked (free sale)
- 25 of 25100% · 31 rehab units
- Buildings
- 20.3 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale25 booked out of 25 units
Rehab31 units for existing members
Total 56 units. Rehab units are not for sale.
Project facts
- 1 RK
- 1
- 1 BHK
- 19
- 2 BHK
- 16
- 3 BHK
- 20
- Total units
- 56
- Buildings
- 2
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 25
- Rehab units
- 31
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 95% | 97% | 25 | |
| 100% | 100% | 95% | 25 | |
| 100% | 100% | 97% | 19 | |
| 100% | 95% | 55% | 9 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400071
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 6 mths | 3 yrs 6 mths |
| Possession date extended | By 2 yrs 8 mths | 4 of 4 |
| Possession date (MahaRERA) | Apr 2027 | Dec 2026 |
| Concrete structure (RCC) | 95% | 45% |
| Units booked (free sale) | 100% | 44% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 4 projects
- Nirvaana Emerald, Chembur
- Nirvaana Crown, Chembur
- Janki Heritage, Chembur
- Nirvaana Solitaire, Chembur
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Nirvaana Emerald | March 2022 | December 2026 | 50% | 12 units booked out of 27 units for sale |
| Nirvaana Crown | November 2021 | October 2027 | 0% | – |
| Janki Heritage | June 2022 | December 2025 | 100% | 17 units booked out of 42 units for sale |
| Nirvaana Solitaire | June 2022 | December 2026 | 40% | 10 units booked out of 22 units for sale |
About this project
Sidhivinayak Flora by Sidhivinayak Constructions is a 56-unit BMC-sanctioned project in Chembur, Mumbai 400071, launched in February 2022 with possession due in April 2027. 25 units booked out of 25 units for sale. The concrete structure (RCC) is 95% complete.
Read full summary
Sidhivinayak Flora is a BMC-sanctioned project by Sidhivinayak Constructions in Chembur, Mumbai 400071, registered with MahaRERA as P51800033003. It was launched in February 2022. It has 56 units in 2 buildings, with 1 RK, 1 BHK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 56 units, 25 are for sale and 31 are rehab units for existing members.
Its registered possession date is April 2027, extended by 2 years 8 months from the original August 2024. Construction: excavation complete, structure (RCC) 95% complete, final finishes 97% complete.
25 units booked out of 25 units for sale (100%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 100% to 95% and the possession date has moved from August 2025 to April 2027.