Nirvaana Emerald, Chembur

by Nirvaana Lifespace LLP · Chembur, Mumbai 400071 · Map

Launched
Mar 20223 yrs 9 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 1 yr
Concrete structure
50%Mid-construction
Booked (free sale)
12 of 2744% · 25 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale12 booked out of 27 units

Rehab25 units for existing members

Total 52 units. Rehab units are not for sale.

Project facts

1 BHK
26
2 BHK
17
3 BHK
9
Total units
52
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
27
Rehab units
25

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation70%
Concrete structure (slabs)50%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 70%Oct 2026: Excavation 70%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 50%Oct 2026: Concrete structure (RCC) 50%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 70%Concrete structure (RCC) 50%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
70%50%0%12
70%50%0%12
0%0%0%12
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400071

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 9 mths2 yrs 6 mths
Possession date extendedBy 1 yr3 of 3
Possession date (MahaRERA)Dec 2026Apr 2027
Concrete structure (RCC)50%95%
MahaRERA complaints (filed by or against the builder)01

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Nirvaana Emerald by Nirvaana Lifespace LLP is a 52-unit MHADA-sanctioned project in Chembur, Mumbai 400071, launched in March 2022 with possession due in December 2026. 12 units booked out of 27 units for sale. The concrete structure (RCC) is 50% complete.

Read full summary

Nirvaana Emerald is a MHADA-sanctioned project by Nirvaana Lifespace LLP in Chembur, Mumbai 400071, registered with MahaRERA as P51800033884. It was launched in March 2022. It has 52 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 52 units, 27 are for sale and 25 are rehab units for existing members.

Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation 70% complete, structure (RCC) 50% complete, final finishes not started.

12 units booked out of 27 units for sale (44%).