Kcd Emerald, Kandivali West
Lapsed
by Kcd Heritage Private Limited · Kandivali West, Mumbai 400067 · Map
- Launched
- Feb 20222 yrs 4 mths promised
- Possession (MahaRERA)
- Jun 2024Not extendedWhat does Lapsed mean?
- Concrete structure
- 1%Mid-construction
- Booked
- 14 of 1593%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 12
- 2 BHK
- 1
- Other units
- 2
- Total units
- 15
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 1% | 0% | 14 | |
| 100% | 1% | 0% | – | |
| 100% | 1% | 0% | – | |
| 100% | 1% | 0% | 14 |
"–" means MahaRERA shows no figure for that update.
About this project
Kcd Emerald by Kcd Heritage Private Limited is a 15-unit project in Kandivali West, Mumbai 400067, launched in February 2022; its MahaRERA registration has lapsed. 14 units booked out of total 15 units. The concrete structure (RCC) is 1% complete.
Read full summary
Kcd Emerald is a project by Kcd Heritage Private Limited in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800033322. It was launched in February 2022. It has 15 units in 1 building: 13 homes (1 and 2 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2024. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 1% complete, final finishes not started.
14 units booked out of total 15 units (93%).