Monte Verita - East Tower, Borivali East

by M/s B G Shirke Redevelopment and GAS P L · Borivali East, Mumbai 400066 · Map

Launched
Mar 20225 yrs promised
Possession (MahaRERA)
Mar 2027Not extended
Concrete structure
0%Early stage
Booked
152 of 21770%
Buildings
10.5 acres
MahaRERA complaints
9Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
67
2 BHK
141
3 BHK
2
Other units
7
Total units
217
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
9

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%152
100%0%0%–
100%0%0%–
100%0%0%152

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400066

Projects with 100–450 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400066
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs4 yrs 11 mths
Possession date extendedNo1 of 3
Possession date (MahaRERA)Mar 2027Dec 2026
Concrete structure (RCC)0%100%
MahaRERA complaints (filed by or against the builder)91

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Monte Verita - East Tower by M/s B G Shirke Redevelopment and GAS P L is a 217-unit MHADA-sanctioned project in Borivali East, Mumbai 400066, launched in March 2022 with possession due in March 2027. 152 units booked out of total 217 units. Work on the concrete structure (RCC) has not started.

Read full summary

Monte Verita - East Tower is a MHADA-sanctioned project by M/s B G Shirke Redevelopment and GAS P L in Borivali East, Mumbai 400066, registered with MahaRERA as P51800033728. It was launched in March 2022. It has 217 units in 1 building: 210 homes (1, 2 and 3 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

152 units booked out of total 217 units (70%).