RAGHAV Paradise, Borivali East

Ready to moveLapsed

by Veda Infra Projects · Borivali East, Mumbai 400066 · Map

Launched
May 20222 yrs 7 mths originally promised
Possession (MahaRERA)
Dec 2025Extended by 1 yrWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
118 of 19760%
Buildings
10.7 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
106
2 BHK
43
3 BHK
43
Other units
5
Total units
197
Buildings
1
Land
0.7 acres
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 90%Jul 2026: Final finishes 90%Oct 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%118
100%100%90%–
100%100%90%–
100%0%0%118

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400066

Projects with 90–400 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400066
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 7 mths4 yrs 11 mths
Possession date extendedBy 1 yr1 of 5
Possession date (MahaRERA)Dec 2025Dec 2026
Concrete structure (RCC)100%76%
Units booked60%71%
MahaRERA complaints (filed by or against the builder)21

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

RAGHAV Paradise by Veda Infra Projects is a 197-unit SRA-sanctioned project in Borivali East, Mumbai 400066, launched in May 2022; its MahaRERA registration has lapsed. 118 units booked out of total 197 units. The concrete structure (RCC) is complete.

Read full summary

RAGHAV Paradise is an SRA-sanctioned project by Veda Infra Projects in Borivali East, Mumbai 400066, registered with MahaRERA as P51800045345. It was launched in May 2022. It has 197 units in 1 building: 192 homes (1, 2 and 3 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025, after an extension of 1 year from the original December 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

118 units booked out of total 197 units (60%).