- Launched
- Mar 20221 yr 11 mths promised
- Possession (MahaRERA)
- Feb 2024Not extendedWhat does Lapsed mean?
- Concrete structure
- 45%Mid-construction
- Booked (free sale)
- 1 of 520%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale1 booked out of 5 units
Land-owner share8 units, not for sale
Total 13 units. Land-owner units are not for sale.
Project facts
- 4 BHK
- 13
- Total units
- 13
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 5
- Land-owner share (not for sale)
- 8
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 45% | 0% | 1 | |
| 100% | 45% | 0% | 1 | |
| 100% | 45% | 0% | 1 | |
| 100% | 45% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400071
Projects with up to 30 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 11 mths | 2 yrs 10 mths |
| Possession date extended | No | 2 of 3 |
| Possession date (MahaRERA) | Feb 2024 | Apr 2027 |
| Concrete structure (RCC) | 45% | 100% |
| Units booked (free sale) | 20% | 43% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Sampoorna, Chembur
- Abhilash Phase II, Chembur
- Sapphire Tower, Chembur
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sampoorna | April 2022 | April 2027 | 100% | 7 units booked out of 10 units for sale |
| Abhilash Phase II | February 2022 | March 2027 | 100% | 6 units booked out of total 14 units |
| Sapphire Tower | January 2022 | May 2027 | 30% | 3 units booked out of total 15 units |
About this project
Rajita Villa by Siddharth Enterprises is a 13-unit project in Chembur, Mumbai 400071, launched in March 2022; its MahaRERA registration has lapsed. 1 unit booked out of 5 units for sale. The concrete structure (RCC) is 45% complete.
Read full summary
Rajita Villa is a project by Siddharth Enterprises in Chembur, Mumbai 400071, registered with MahaRERA as P51800033778. It was launched in March 2022. It has 13 units in 1 building, with 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 13 units, 5 are for sale and 8 are the land-owner's share, not for sale.
Possession was due in February 2024. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 45% complete, final finishes not started.
1 unit booked out of 5 units for sale (20%).