Kush Pride, Kandivali West
by Kush Housing LLP · Kandivali West, Mumbai 400067 · Map
- Launched
- Mar 20223 yrs 9 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 1 yr
- Concrete structure
- 98%Mid-construction
- Booked (free sale)
- 32 of 3689% · 53 rehab units
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale32 booked out of 36 units
Rehab53 units for existing members
Total 89 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 17
- 2 BHK
- 36
- 3 BHK
- 17
- 4 BHK
- 3
- Other units
- 16
- Total units
- 89
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 36
- Rehab units
- 53
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 98% | 94% | 32 | |
| 100% | 97% | 80% | 32 | |
| 100% | 92% | 50% | 32 | |
| 100% | 90% | 20% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400067
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 9 mths | 3 yrs 11 mths |
| Possession date extended | By 1 yr | 3 of 6 |
| Possession date (MahaRERA) | Dec 2026 | Dec 2026 |
| Concrete structure (RCC) | 98% | 100% |
| Units booked (free sale) | 89% | 72% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Shree Vrindavan, Kandivali West
- Charkop Kshitij Chs Ltd, Kandivali West
- Charkop Jeevan Mangal C.H.S. Ltd, Kandivali West
- Orion Heights, Kandivali West
- Om Shreenath Krupa Chs Ltd, Kandivali West
- Charkop Priyanka Cooperative Housing Society Limited, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shree Vrindavan | March 2022 | June 2027 | 93% | 29 units booked out of 42 units for sale |
| Charkop Kshitij Chs Ltd | April 2022 | December 2026 | 100% | 55 units booked out of 59 units for sale |
| Charkop Jeevan Mangal C.H.S. Ltd | April 2022 | June 2026 | 100% | 24 units booked out of total 44 units |
| Orion Heights | April 2022 | March 2027 | 100% | 73 units booked out of 111 units for sale |
| Om Shreenath Krupa Chs Ltd | December 2021 | December 2026 | 100% | 21 units booked out of 28 units for sale |
| Charkop Priyanka Cooperative Housing Society Limited | June 2022 | October 2026 | 100% | 43 units booked out of 55 units for sale |
About this project
Kush Pride by Kush Housing LLP is an 89-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in March 2022 with possession due in December 2026. 32 units booked out of 36 units for sale. The concrete structure (RCC) is 98% complete.
Read full summary
Kush Pride is a BMC-sanctioned project by Kush Housing LLP in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800033962. It was launched in March 2022. It has 89 units in 1 building: 73 homes (1, 2, 3 and 4 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 89 units, 36 are for sale and 53 are rehab units for existing members.
Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) 98% complete, final finishes 94% complete.
32 units booked out of 36 units for sale (89%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 97% to 98% and the possession date has moved from June 2026 to December 2026.