Charkop Jeevan Mangal C.H.S. Ltd, Kandivali West

Ready to moveLapsed

by Sandhya Kshitij Builders Private Limited · Kandivali West, Mumbai 400067 · Map

Launched
Apr 20222 yrs 6 mths originally promised
Possession (MahaRERA)
Jun 2026Extended by 1 yr 8 mthsWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
24 of 4455%
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
8
2 BHK
31
Other units
5
Total units
44
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 60%Dec 2025: Final finishes 60%Jul 2026: Final finishes 100%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%24
100%100%100%–
100%100%60%–
100%100%60%24

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400067

Projects with 10–80 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 6 mths3 yrs 4 mths
Possession date extendedBy 1 yr 8 mths3 of 6
Possession date (MahaRERA)Jun 2026Dec 2026
Concrete structure (RCC)100%99%
Units booked55%91%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Charkop Jeevan Mangal C.H.S. Ltd by Sandhya Kshitij Builders Private Limited is a 44-unit MHADA-sanctioned project in Kandivali West, Mumbai 400067, launched in April 2022; its MahaRERA registration has lapsed. 24 units booked out of total 44 units. The concrete structure (RCC) is complete.

Read full summary

Charkop Jeevan Mangal C.H.S. Ltd is a MHADA-sanctioned project by Sandhya Kshitij Builders Private Limited in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800034943. It was launched in April 2022. It has 44 units in 1 building: 39 homes (1 and 2 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2026, after an extension of 1 year 8 months from the original October 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

24 units booked out of total 44 units (55%).