Rajshree Forty Three East, Ghatkopar East
Ready to moveLapsed
by Rajshree Shivkunj Developers LLP · Ghatkopar East, Mumbai 400075 · Map
- Launched
- Mar 20223 yrs 3 mths originally promised
- Possession (MahaRERA)
- Dec 2025Extended by 6 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 79 of 79100% · 30 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale79 booked out of 79 units
Rehab30 units for existing members
Total 109 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 16
- 2 BHK
- 78
- 3 BHK
- 14
- Other units
- 1
- Total units
- 109
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 79
- Rehab units
- 30
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 79 | |
| 100% | 100% | 95% | 79 | |
| 100% | 100% | 95% | 79 | |
| 100% | 75% | 5% | 62 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400075
Projects with 50–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 3 mths | 3 yrs 6 mths |
| Possession date extended | By 6 mths | 2 of 4 |
| Possession date (MahaRERA) | Dec 2025 | Jul 2026 |
| Concrete structure (RCC) | 100% | 98% |
| Units booked (free sale) | 100% | 74% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Aryana Heights, Ghatkopar East
- Choice Ambe Krupa, Ghatkopar East
- Omkaar Pride, Ghatkopar East
- Shivneri Chs Adityaraj Gateway, Ghatkopar East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Aryana Heights | April 2022 | March 2027 | 100% | 52 units booked out of 60 units for sale |
| Choice Ambe Krupa | June 2022 | December 2025 | 95% | 79 units booked out of 79 units for sale |
| Omkaar Pride | December 2021 | July 2027 | 92% | 46 units booked out of total 99 units |
| Shivneri Chs Adityaraj Gateway | June 2022 | December 2025 | 100% | 78 units booked out of total 129 units |
About this project
Rajshree Forty Three East by Rajshree Shivkunj Developers LLP is a 109-unit MHADA-sanctioned project in Ghatkopar East, Mumbai 400075, launched in March 2022; its MahaRERA registration has lapsed. 79 units booked out of 79 units for sale. The concrete structure (RCC) is complete.
Read full summary
Rajshree Forty Three East is a MHADA-sanctioned project by Rajshree Shivkunj Developers LLP in Ghatkopar East, Mumbai 400075, registered with MahaRERA as P51800034083. It was launched in March 2022. It has 109 units in 1 building: 108 homes (1, 2 and 3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 109 units, 79 are for sale and 30 are rehab units for existing members.
Possession was due in December 2025, after an extension of 6 months from the original June 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
79 units booked out of 79 units for sale (100%).